Dept. of Trans. PROGRESS Serial No. Contract No. 03-112-17-30 04-006044 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 46% 04-CC-680-24.6/25.1 Federal Project: ACIM-680-1(54) Progress payment No. 12 Payment period ending: 04-20-03 WEST BAY BUILDERS INC P O BOX 3474 SAN RAFAEL CA 949123474 Escrow No. 01920 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,635,411.00 726,608.50 2.a. Extra Work 54,169.88 26,278.38 b. Adjustment Comp. -1,519.41 1,655.63 3. Materials on Hand 4. Earned Subject to Retention 6,688,061.47 754,542.51 5. Mobilization 6. Total Work Completed 6,688,061.47 7. Deductions -2,350.94 113,042.00 8. a.Contract Retentions -381,429.93 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,304,280.60 867,584.51 10. Reduction Amt to Escrow 11. Payment to Escrow 381,420.00 12. Net Pymt. this Estimate 867,584.51