Dept. of Trans. PROGRESS Serial No. Contract No. 03-232-12-11 04-006044 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 62% 04-CC-680-24.6/25.1 Federal Project: ACIM-680-1(54) Progress payment No. 16 Payment period ending: 08-20-03 WEST BAY BUILDERS INC P O BOX 3474 SAN RAFAEL CA 949123474 Escrow No. 01920 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,408,496.00 750,108.50 2.a. Extra Work 54,956.88 505.60 b. Adjustment Comp. 61,785.46 19,398.78 3. Materials on Hand 4. Earned Subject to Retention 9,525,238.34 770,012.88 5. Mobilization 6. Total Work Completed 9,525,238.34 7. Deductions -2,350.94 0.00 8. a.Contract Retentions -476,261.92 -38,500.65 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,046,625.48 731,512.23 10. Reduction Amt to Escrow 11. Payment to Escrow 476,260.00 12. Net Pymt. this Estimate 731,512.23