Dept. of Trans. PROGRESS Serial No. Contract No. 03-353-13-28 04-006044 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 59% 04-CC-680-24.6/25.1 Federal Project: ACIM-680-1(54) Progress payment No. 20 Payment period ending: 12-20-03 WEST BAY BUILDERS INC P O BOX 3474 SAN RAFAEL CA 949123474 Escrow No. 01920 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,893,006.90 245,471.90 2.a. Extra Work 162,981.33 52,374.93 b. Adjustment Comp. 246,669.80 23,518.31 3. Materials on Hand 4. Earned Subject to Retention 11,302,658.03 321,365.14 5. Mobilization 6. Total Work Completed 11,302,658.03 7. Deductions -2,350.94 0.00 8. a.Contract Retentions -565,132.90 -16,068.26 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,735,174.19 305,296.88 10. Reduction Amt to Escrow 11. Payment to Escrow 565,130.00 12. Net Pymt. this Estimate 305,296.88