Dept. of Trans. PROGRESS Serial No. Contract No. 04-079-12-51 04-006044 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 51% 04-CC-680-24.6/25.1 Federal Project: ACIM-680-1(54) Progress payment No. 23 Payment period ending: 03-20-04 WEST BAY BUILDERS INC P O BOX 3474 SAN RAFAEL CA 949123474 Escrow No. 01920 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,475,787.40 804,631.00 2.a. Extra Work 476,757.49 5,836.75 b. Adjustment Comp. 321,305.60 24,259.49 3. Materials on Hand 4. Earned Subject to Retention 13,273,850.49 834,727.24 5. Mobilization 6. Total Work Completed 13,273,850.49 7. Deductions -2,350.94 0.00 8. a.Contract Retentions -663,692.52 -41,736.36 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,607,807.03 792,990.88 10. Reduction Amt to Escrow 11. Payment to Escrow 663,690.00 12. Net Pymt. this Estimate 792,990.88