Dept. of Trans. PROGRESS Serial No. Contract No. 04-118-12-08 04-006044 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 53% 04-CC-680-24.6/25.1 Federal Project: ACIM-680-1(54) Progress payment No. 24 Payment period ending: 04-20-04 WEST BAY BUILDERS INC P O BOX 3474 SAN RAFAEL CA 949123474 Escrow No. 01920 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,725,912.80 250,125.40 2.a. Extra Work 1,095,124.43 618,366.94 b. Adjustment Comp. 307,248.40 -14,057.20 3. Materials on Hand 4. Earned Subject to Retention 14,128,285.63 854,435.14 5. Mobilization 6. Total Work Completed 14,128,285.63 7. Deductions -2,350.94 0.00 8. a.Contract Retentions -706,414.28 -42,721.76 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,419,520.41 811,713.38 10. Reduction Amt to Escrow 11. Payment to Escrow 706,410.00 12. Net Pymt. this Estimate 811,713.38