Dept. of Trans. PROGRESS Serial No. Contract No. 07-087-08-00 04-006044 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-CC-680-24.6/25.1 Federal Project: ACIM-680-1(54) Progress payment No. 56 Payment period ending: 03-20-07 WEST BAY BUILDERS INC 250 BEL MARIN KEYS BLVD BLDG NAVATO CA 94949 Escrow No. 01920 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,736,470.13 0.00 2.a. Extra Work 1,883,240.07 5,442.96 b. Adjustment Comp. 552,530.93 2,558.27 3. Materials on Hand 4. Earned Subject to Retention 22,172,241.13 8,001.23 5. Mobilization 6. Total Work Completed 22,172,241.13 7. Deductions -13,250.94 0.00 8. a.Contract Retentions -1,108,612.06 -400.06 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,050,378.13 7,601.17 10. Reduction Amt to Escrow 11. Payment to Escrow 1,108,610.00 12. Net Pymt. this Estimate 7,601.17