Dept. of Trans. PROGRESS Serial No. Contract No. 04-083-10-06 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 67% 62% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 19 Payment period ending: 03-20-04 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,028,982.97 -16,052.08 2.a. Extra Work 8,099,350.23 996,550.78 b. Adjustment Comp. 160,378.00 65,000.00 3. Materials on Hand 3,120,342.10 -385,832.39 4. Earned Subject to Retention 26,409,053.30 659,666.31 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 27,138,711.20 7. Deductions 8. a.Contract Retentions -1,320,452.67 -32,983.32 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 28,938,600.63 626,682.99 10. Reduction Amt to Escrow 11. Payment to Escrow 1,320,450.00 12. Net Pymt. this Estimate 626,682.99