Dept. of Trans. PROGRESS Serial No. Contract No. 04-146-07-10 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 54% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 21 Payment period ending: 05-24-04 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,303,448.86 1,135,430.93 2.a. Extra Work 12,969,784.32 4,314,662.67 b. Adjustment Comp. -3,583,583.05 -3,743,961.05 3. Materials on Hand 2,923,957.66 -47,925.00 4. Earned Subject to Retention 28,613,607.79 1,658,207.55 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 29,539,650.13 7. Deductions 8. a.Contract Retentions -1,430,680.39 -82,910.38 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 31,032,927.40 1,575,297.17 10. Reduction Amt to Escrow 11. Payment to Escrow 1,430,680.00 12. Net Pymt. this Estimate 1,575,297.17