Dept. of Trans. PROGRESS Serial No. Contract No. 04-173-12-41 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 57% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 22 Payment period ending: 06-20-04 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,862,037.39 558,588.53 2.a. Extra Work 13,377,024.92 407,240.60 b. Adjustment Comp. -3,581,476.16 2,106.89 3. Materials on Hand 2,971,046.77 47,089.11 4. Earned Subject to Retention 29,628,632.92 1,015,025.13 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 30,507,586.15 7. Deductions 8. a.Contract Retentions -1,481,431.65 -50,751.26 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 31,997,201.27 964,273.87 10. Reduction Amt to Escrow 11. Payment to Escrow 1,481,430.00 12. Net Pymt. this Estimate 964,273.87