Dept. of Trans. PROGRESS Serial No. Contract No. 04-202-20-17 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 60% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 23 Payment period ending: 07-20-03 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,996,278.31 1,134,240.92 2.a. Extra Work 13,952,409.86 575,384.94 b. Adjustment Comp. -3,534,789.51 46,686.65 3. Materials on Hand 2,556,793.56 -414,253.21 4. Earned Subject to Retention 30,970,692.22 1,342,059.30 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 32,263,898.66 7. Deductions 8. a.Contract Retentions -1,548,534.61 -67,102.96 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 33,272,157.61 1,274,956.34 10. Reduction Amt to Escrow 11. Payment to Escrow 1,548,530.00 12. Net Pymt. this Estimate 1,274,956.34