Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 04-245-08-38 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 64% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 25 Payment period ending: 08-31-04 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,962,046.02 20,333.50 2.a. Extra Work 14,186,459.75 0.00 b. Adjustment Comp. -3,521,781.20 0.00 3. Materials on Hand 3,108,616.00 888,999.92 4. Earned Subject to Retention 32,735,340.57 909,333.42 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 33,476,724.57 7. Deductions 8. a.Contract Retentions -1,636,767.03 -45,466.67 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 34,948,573.54 863,866.75 10. Reduction Amt to Escrow 11. Payment to Escrow 1,636,760.00 12. Net Pymt. this Estimate 863,866.75