Dept. of Trans. PROGRESS Serial No. Contract No. 04-294-09-51 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 68% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 27 Payment period ending: 10-20-04 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,332,637.76 1,555,071.73 2.a. Extra Work 14,474,134.44 185,262.67 b. Adjustment Comp. -3,520,423.96 0.00 3. Materials on Hand 3,034,712.47 74,177.01 4. Earned Subject to Retention 35,321,060.71 1,814,511.41 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 36,136,348.24 7. Deductions 8. a.Contract Retentions -1,766,053.04 -90,725.57 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 37,405,007.67 1,723,785.84 10. Reduction Amt to Escrow 11. Payment to Escrow 1,766,050.00 12. Net Pymt. this Estimate 1,723,785.84