Dept. of Trans. PROGRESS Serial No. Contract No. 04-329-09-22 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 70% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 28 Payment period ending: 11-20-04 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,896,688.91 1,564,051.15 2.a. Extra Work 14,692,907.13 218,772.69 b. Adjustment Comp. -3,497,599.68 22,824.28 3. Materials on Hand 3,444,619.74 409,907.27 4. Earned Subject to Retention 37,536,616.10 2,215,555.39 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 37,941,996.36 7. Deductions 8. a.Contract Retentions -1,876,830.81 -110,777.77 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 39,509,785.29 2,104,777.62 10. Reduction Amt to Escrow 11. Payment to Escrow 1,876,830.00 12. Net Pymt. this Estimate 2,104,777.62