Dept. of Trans. PROGRESS Serial No. Contract No. 04-355-14-04 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 73% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 29 Payment period ending: 12-20-04 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,248,129.38 1,351,440.47 2.a. Extra Work 15,152,772.42 459,865.29 b. Adjustment Comp. -3,119,599.68 378,000.00 3. Materials on Hand 2,716,915.46 -727,704.28 4. Earned Subject to Retention 38,998,217.58 1,461,601.48 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 40,131,302.12 7. Deductions 8. a.Contract Retentions -1,949,910.88 -73,080.07 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 40,898,306.70 1,388,521.41 10. Reduction Amt to Escrow 11. Payment to Escrow 1,949,910.00 12. Net Pymt. this Estimate 1,388,521.41