Dept. of Trans. PROGRESS Serial No. Contract No. 05-019-09-16 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 75% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 30 Payment period ending: 01-20-05 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,726,274.44 478,145.06 2.a. Extra Work 15,672,113.10 519,340.68 b. Adjustment Comp. -3,119,599.68 0.00 3. Materials on Hand 2,169,607.18 -547,308.28 4. Earned Subject to Retention 39,448,395.04 450,177.46 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 41,128,787.86 7. Deductions 8. a.Contract Retentions -1,972,419.75 -22,508.87 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 41,325,975.29 427,668.59 10. Reduction Amt to Escrow 11. Payment to Escrow 1,972,410.00 12. Net Pymt. this Estimate 427,668.59