Dept. of Trans. PROGRESS Serial No. Contract No. 05-050-07-07 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 78% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 31 Payment period ending: 02-20-05 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,304,601.17 578,326.73 2.a. Extra Work 15,755,951.71 83,838.61 b. Adjustment Comp. -3,119,599.68 0.00 3. Materials on Hand 2,007,360.90 -162,246.28 4. Earned Subject to Retention 39,948,314.10 499,919.06 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 41,790,953.20 7. Deductions 8. a.Contract Retentions -1,997,415.71 -24,995.96 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 41,800,898.39 474,923.10 10. Reduction Amt to Escrow 11. Payment to Escrow 1,997,410.00 12. Net Pymt. this Estimate 474,923.10