Dept. of Trans. PROGRESS Serial No. Contract No. 05-140-17-19 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 83% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 34 Payment period ending: 05-20-05 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,562,007.47 393,635.59 2.a. Extra Work 16,301,032.77 73,602.35 b. Adjustment Comp. -2,746,951.58 0.00 3. Materials on Hand 1,599,448.10 36,605.13 4. Earned Subject to Retention 41,715,536.76 503,843.07 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 43,966,088.66 7. Deductions 8. a.Contract Retentions -2,085,776.84 -25,192.16 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 43,479,759.92 478,650.91 10. Reduction Amt to Escrow 11. Payment to Escrow 2,085,770.00 12. Net Pymt. this Estimate 478,650.91