Dept. of Trans. PROGRESS Serial No. Contract No. 05-167-11-03 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 85% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 35 Payment period ending: 06-20-05 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,074,343.43 512,335.96 2.a. Extra Work 16,426,279.27 125,246.50 b. Adjustment Comp. -2,746,951.58 0.00 3. Materials on Hand 2,520,864.83 921,416.73 4. Earned Subject to Retention 43,274,535.95 1,558,999.19 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 44,603,671.12 7. Deductions 8. a.Contract Retentions -2,163,726.80 -77,949.96 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 44,960,809.15 1,481,049.23 10. Reduction Amt to Escrow 11. Payment to Escrow 2,163,720.00 12. Net Pymt. this Estimate 1,481,049.23