Dept. of Trans. PROGRESS Serial No. Contract No. 05-201-15-14 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 88% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 36 Payment period ending: 07-20-05 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,582,609.46 508,266.03 2.a. Extra Work 16,560,817.54 134,538.27 b. Adjustment Comp. -2,724,451.58 22,500.00 3. Materials on Hand 2,521,997.80 1,132.97 4. Earned Subject to Retention 43,940,973.22 666,437.27 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 45,268,975.42 7. Deductions 8. a.Contract Retentions -2,197,048.66 -33,321.86 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 45,593,924.56 633,115.41 10. Reduction Amt to Escrow 11. Payment to Escrow 2,197,040.00 12. Net Pymt. this Estimate 633,115.41