Dept. of Trans. PROGRESS Serial No. Contract No. 05-232-08-31 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 91% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 37 Payment period ending: 08-20-05 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,914,492.86 331,883.40 2.a. Extra Work 17,608,787.34 1,047,969.80 b. Adjustment Comp. -2,686,003.58 38,448.00 3. Materials on Hand 2,591,079.68 69,081.88 4. Earned Subject to Retention 45,428,356.30 1,487,383.08 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 46,687,276.62 7. Deductions 8. a.Contract Retentions -2,271,417.82 -74,369.16 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 47,006,938.48 1,413,013.92 10. Reduction Amt to Escrow 11. Payment to Escrow 2,271,410.00 12. Net Pymt. this Estimate 1,413,013.92