Dept. of Trans. PROGRESS Serial No. Contract No. 05-263-09-45 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 94% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 38 Payment period ending: 09-20-05 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,368,598.86 454,106.00 2.a. Extra Work 17,658,656.35 49,869.01 b. Adjustment Comp. -2,686,003.58 0.00 3. Materials on Hand 2,463,267.59 -127,812.09 4. Earned Subject to Retention 45,804,519.22 376,162.92 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 47,191,251.63 7. Deductions 8. a.Contract Retentions -2,290,225.96 -18,808.14 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 47,364,293.26 357,354.78 10. Reduction Amt to Escrow 11. Payment to Escrow 2,290,220.00 12. Net Pymt. this Estimate 357,354.78