Dept. of Trans. PROGRESS Serial No. Contract No. 05-325-14-01 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 99% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 40 Payment period ending: 11-20-05 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,260,335.05 587,416.90 2.a. Extra Work 17,785,981.27 59,845.45 b. Adjustment Comp. -2,686,003.58 0.00 3. Materials on Hand 2,347,389.81 8,788.12 4. Earned Subject to Retention 46,707,702.55 656,050.47 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 48,210,312.74 7. Deductions 8. a.Contract Retentions -2,335,385.13 -32,802.53 b. Unsatisfactory Prog. -45,159.16 -32,802.52 c. Reduction after 95% Comp. 9. Total pay to Contractor 48,177,158.26 590,445.42 10. Reduction Amt to Escrow 11. Payment to Escrow 2,335,380.00 12. Net Pymt. this Estimate 590,445.42