Dept. of Trans. PROGRESS Serial No. Contract No. 05-354-07-27 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 100% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 41 Payment period ending: 12-20-05 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,128,189.80 867,854.75 2.a. Extra Work 17,814,559.90 28,578.63 b. Adjustment Comp. -2,652,245.46 33,758.12 3. Materials on Hand 2,047,789.99 -299,599.82 4. Earned Subject to Retention 47,338,294.23 630,591.68 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 49,140,504.24 7. Deductions 8. a.Contract Retentions -2,366,914.71 -31,529.58 b. Unsatisfactory Prog. 0.00 45,159.16 c. Reduction after 95% Comp. 9. Total pay to Contractor 48,821,379.52 644,221.26 10. Reduction Amt to Escrow 11. Payment to Escrow 2,366,910.00 12. Net Pymt. this Estimate 644,221.26