Dept. of Trans. PROGRESS Serial No. Contract No. 06-110-07-09 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 45 Payment period ending: 04-20-06 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,565,524.16 84,182.25 2.a. Extra Work 18,118,136.05 156,124.71 b. Adjustment Comp. -2,597,585.13 0.00 3. Materials on Hand 1,878,943.00 -196,702.00 4. Earned Subject to Retention 48,965,018.08 43,604.96 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 50,936,075.08 7. Deductions 8. a.Contract Retentions -2,448,250.90 -2,180.24 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 50,366,767.18 41,424.72 10. Reduction Amt to Escrow 11. Payment to Escrow 2,448,250.00 12. Net Pymt. this Estimate 41,424.72