Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-192-14-02 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 47 Payment period ending: 05-12-06 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,569,390.62 57,947.30 2.a. Extra Work 20,182,117.95 65,452.62 b. Adjustment Comp. -1,904,739.26 0.00 3. Materials on Hand 4. Earned Subject to Retention 49,846,769.31 123,399.92 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 53,696,769.31 7. Deductions 8. a.Contract Retentions -2,448,250.90 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,448,250.90 0.00 9. Total pay to Contractor 53,696,769.31 123,399.92 10. Reduction Amt to Escrow -2,448,250.00 0.00 11. Payment to Escrow 2,448,250.00 12. Net Pymt. this Estimate 123,399.92