Dept. of Trans. FINAL Serial No. Contract No. 07-101-09-24 04-006054 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-CC-680-23.9/24.9 Federal Project: ACIM-680-1(54) Progress payment No. 52 Payment period ending: 05-12-06 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA, CA 94510 Escrow No. 01982 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,649,991.25 1,400.00 2.a. Extra Work 20,347,099.99 26,500.00 b. Adjustment Comp. -656,920.43 0.00 3. Materials on Hand 4. Earned Subject to Retention 51,340,170.81 27,900.00 5. Mobilization 3,850,000.00 0.00 6. Total Work Completed 55,190,170.81 7. Deductions 8. a.Contract Retentions -2,448,250.90 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,448,250.90 0.00 9. Total pay to Contractor 55,190,170.81 27,900.00 10. Reduction Amt to Escrow -2,448,250.00 0.00 11. Payment to Escrow 2,448,250.00 12. Net Pymt. this Estimate 27,900.00