Dept. of Trans. PROGRESS Serial No. Contract No. 02-354-13-49 04-006064 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 30% 04-SOL-680-L0.3/1.0 Federal Project: 04-SOL-780-0.7/1.5 ACIM-680-1(54) Progress payment No. 11 Payment period ending: 12-20-02 C C MYERS INC P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 01868 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,440,967.01 1,283,546.55 2.a. Extra Work 419,176.49 115,665.60 b. Adjustment Comp. 153,484.37 446.00 3. Materials on Hand 4,062,899.28 19,014.66 4. Earned Subject to Retention 16,076,527.15 1,418,672.81 5. Mobilization 6,080,000.00 0.00 6. Total Work Completed 18,093,627.87 7. Deductions 8. a.Contract Retentions -1,171,182.17 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,985,344.98 1,418,672.81 10. Reduction Amt to Escrow 11. Payment to Escrow 1,171,180.00 12. Net Pymt. this Estimate 1,418,672.81