Dept. of Trans. PROGRESS Serial No. Contract No. 05-167-16-58 04-006064 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 98% 04-SOL-680-L0.3/1.0 Federal Project: 04-SOL-780-0.7/1.5 ACIM-680-1(54) Progress payment No. 41 Payment period ending: 06-20-05 C C MYERS INC P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 01868 Total Estimate This Estimate 1. Contract Itms Without Mobil. 49,882,715.76 1,066,772.90 2.a. Extra Work 3,648,334.08 168,745.91 b. Adjustment Comp. 2,513,652.47 30,892.95 3. Materials on Hand 357,583.37 -206,565.11 4. Earned Subject to Retention 56,402,285.68 1,059,846.65 5. Mobilization 6,400,000.00 0.00 6. Total Work Completed 62,444,702.31 7. Deductions -31,535.20 0.00 8. a.Contract Retentions -2,820,114.28 -52,992.33 b. Unsatisfactory Prog. -52,992.33 -52,992.33 c. Reduction after 95% Comp. 9. Total pay to Contractor 59,897,643.87 953,861.99 10. Reduction Amt to Escrow 11. Payment to Escrow 2,820,110.00 12. Net Pymt. this Estimate 953,861.99