Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-198-10-44 04-006064 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SOL-680-L0.3/1.0 Federal Project: 04-SOL-780-0.7/1.5 ACIM-680-1(54) Progress payment No. 77 Payment period ending: 03-04-08 C C MYERS INC P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 01868 Total Estimate This Estimate 1. Contract Itms Without Mobil. 61,230,758.09 23,448.40 2.a. Extra Work 9,952,982.09 288,889.13 b. Adjustment Comp. 17,965,461.98 493.20 3. Materials on Hand 4. Earned Subject to Retention 89,149,202.16 312,830.73 5. Mobilization 6,400,000.00 0.00 6. Total Work Completed 95,549,202.16 7. Deductions -26,535.20 20,000.00 8. a.Contract Retentions -4,423,502.57 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 4,423,502.57 0.00 9. Total pay to Contractor 95,522,666.96 332,830.73 10. Reduction Amt to Escrow -4,423,500.00 0.00 11. Payment to Escrow 4,423,500.00 12. Net Pymt. this Estimate 332,830.73