Dept. of Trans. PROGRESS Serial No. Contract No. 05-050-07-07 04-006084 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 25% 04-SOL-680-R1.6/R1.9 Federal Project: NONE Progress payment No. 05 Payment period ending: 02-20-05 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA CA 94510 Escrow No. 02191 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,759,130.45 591,941.55 2.a. Extra Work 37,166.77 37,166.77 b. Adjustment Comp. 3. Materials on Hand 5,612.81 5,612.81 4. Earned Subject to Retention 2,801,910.03 634,721.13 5. Mobilization 451,250.00 0.00 6. Total Work Completed 3,247,547.22 7. Deductions 8. a.Contract Retentions -140,095.50 -31,316.10 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,113,064.53 603,405.03 10. Reduction Amt to Escrow 11. Payment to Escrow 140,090.00 12. Net Pymt. this Estimate 603,405.03