Dept. of Trans. PROGRESS Serial No. Contract No. 05-354-07-27 04-006084 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 85% 04-SOL-680-R1.6/R1.9 Federal Project: NONE Progress payment No. 15 Payment period ending: 12-20-05 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA CA 94510 Escrow No. 02191 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,451,248.25 87,185.22 2.a. Extra Work 304,864.86 10,891.56 b. Adjustment Comp. -42,000.00 -42,000.00 3. Materials on Hand 4. Earned Subject to Retention 5,714,113.11 56,076.78 5. Mobilization 475,000.00 0.00 6. Total Work Completed 6,189,113.11 7. Deductions -8,718.52 -8,718.52 8. a.Contract Retentions -285,705.66 -2,803.84 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,894,688.93 44,554.42 10. Reduction Amt to Escrow 11. Payment to Escrow 285,700.00 12. Net Pymt. this Estimate 44,554.42