Dept. of Trans. PROGRESS Serial No. Contract No. 06-024-13-07 04-006084 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 85% 04-SOL-680-R1.6/R1.9 Federal Project: NONE Progress payment No. 16 Payment period ending: 01-20-06 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA CA 94510 Escrow No. 02191 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,453,048.25 1,800.00 2.a. Extra Work 308,863.49 3,998.63 b. Adjustment Comp. -43,240.98 -1,240.98 3. Materials on Hand 4. Earned Subject to Retention 5,718,670.76 4,557.65 5. Mobilization 475,000.00 0.00 6. Total Work Completed 6,193,670.76 7. Deductions -8,718.52 0.00 8. a.Contract Retentions -285,933.54 -227.88 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,899,018.70 4,329.77 10. Reduction Amt to Escrow 11. Payment to Escrow 285,700.00 12. Net Pymt. this Estimate 4,329.77