Dept. of Trans. PROGRESS Serial No. Contract No. 06-048-09-19 04-006084 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 87% 04-SOL-680-R1.6/R1.9 Federal Project: NONE Progress payment No. 17 Payment period ending: 02-20-06 F C I CONSTRUCTORS INC 2100 GOODYEAR ROAD BENICIA CA 94510 Escrow No. 02191 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,475,534.98 22,486.73 2.a. Extra Work 309,978.85 1,115.36 b. Adjustment Comp. -43,240.98 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,742,272.85 23,602.09 5. Mobilization 475,000.00 0.00 6. Total Work Completed 6,217,272.85 7. Deductions -8,718.52 0.00 8. a.Contract Retentions -287,113.64 -1,180.10 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,921,440.69 22,421.99 10. Reduction Amt to Escrow 11. Payment to Escrow 287,110.00 12. Net Pymt. this Estimate 22,421.99