Dept. of Trans. PROGRESS Serial No. Contract No. 09-147-11-26 04-0060A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 87% 04-CC-680-23.9/25.5 Federal Project: 04-SOL-680-L0.0/L1.0 ACIM-680-1(66) 04-SOL-780-0.7/1.5 ACIM-780-2(351) Progress payment No. 17 Payment period ending: 05-20-09 AMERICAN CIVIL CONSTRUCTORS TOP GRADE CONSTRUCTION J V 50 CONTRACTORS STREET LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,781,640.31 2,668,517.06 2.a. Extra Work 3,439,939.43 227,924.30 b. Adjustment Comp. 1,151,600.08 -62,422.20 3. Materials on Hand 716,152.05 248,455.00 4. Earned Subject to Retention 32,089,331.87 3,082,474.16 5. Mobilization 3,300,000.00 0.00 6. Total Work Completed 34,673,179.82 7. Deductions -8,250.00 -8,250.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 35,381,081.87 3,074,224.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,074,224.16