Dept. of Trans. PROGRESS Serial No. Contract No. 08-201-07-13 04-010904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 14% 04-VAR Federal Project: NONE Progress payment No. 03 Payment period ending: 07-20-08 BLEYCO INCORPORATED 11425 CULL CANYON ROAD CASTRO VALLEY CA 94552 Escrow No. 02367 Total Estimate This Estimate 1. Contract Itms Without Mobil. 318,107.91 137,279.78 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 318,107.91 137,279.78 5. Mobilization 262,563.00 262,563.00 6. Total Work Completed 580,670.91 7. Deductions 8. a.Contract Retentions -31,810.79 -13,727.98 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 548,860.12 386,114.80 10. Reduction Amt to Escrow 11. Payment to Escrow 31,810.00 12. Net Pymt. this Estimate 386,114.80