Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-199-09-15 04-0120E4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SF-80-8.3/8.5 Federal Project: ACBR-080-1(95) IM-080-1(95) Progress payment No. 49 Payment period ending: 01-18-08 KIEWIT F C I MANSON A JOINT VENTURE ALT 2 P O BOX 23223 OAKLAND CA 94623 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 150,771,774.21 0.00 2.a. Extra Work 7,802,000.44 273,264.75 b. Adjustment Comp. 87,792,264.66 -1,510.60 3. Materials on Hand 4. Earned Subject to Retention 246,366,039.31 271,754.15 5. Mobilization 26,617,500.00 0.00 6. Total Work Completed 272,983,539.31 7. Deductions -284,010.05 215,683.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 272,699,529.26 487,437.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 487,437.15