Dept. of Trans. PROGRESS Serial No. Contract No. 09-327-15-24 04-0120F4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 49% 04-SF-80-8.2/8.7 Federal Project: NONE Progress payment No. 43 Payment period ending: 11-20-09 AMERICAN BRIDGE FLUOR ENTERPRISES INC A JOINT VENTURE 1000 AMERICAN BRIDGE WAY CORAOPOLIS PA 15108 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 441,483,827.85 5,264,751.40 2.a. Extra Work 25,634,139.50 511,817.68 b. Adjustment Comp. 259,496,561.40 7,729,637.50 3. Materials on Hand 123,098,854.00 4,616,359.00 4. Earned Subject to Retention 849,713,382.75 18,122,565.58 5. Mobilization 6. Total Work Completed 726,614,528.75 7. Deductions -8,142.20 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 849,705,240.55 18,122,565.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,122,565.58