Dept. of Trans. PROGRESS Serial No. Contract No. 10-202-11-08 04-0120F4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 56% 04-SF-80-8.2/8.7 Federal Project: NONE Progress payment No. 51 Payment period ending: 07-20-10 AMERICAN BRIDGE FLUOR ENTERPRISES INC A JOINT VENTURE 1000 AMERICAN BRIDGE WAY CORAOPOLIS PA 15108 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 703,365,320.25 107,703,140.60 2.a. Extra Work 34,569,317.87 1,792,159.49 b. Adjustment Comp. 304,278,684.18 7,554,144.88 3. Materials on Hand 76,447,227.00 -46,809,323.00 4. Earned Subject to Retention 118,660,549.30 70,240,121.97 5. Mobilization 6. Total Work Completed 42,213,322.30 7. Deductions -1,391,002.82 -549,011.51 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 117,269,546.48 69,691,110.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 69,691,110.46