Dept. of Trans. PROGRESS Serial No. Contract No. 07-142-06-35 04-0120J4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 83% 04-ALA-80-1.6/3.5 Federal Project: NONE Progress payment No. 13 Payment period ending: 05-20-07 DIABLO CONTRACTORS INC 7 CROW CANYON COURT STE 100 SAN RAMON CA 94583 Escrow No. 02281 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,318,627.58 705,335.00 2.a. Extra Work 778,477.30 100,135.71 b. Adjustment Comp. -45,975.79 -9,905.00 3. Materials on Hand 279,150.00 -28,309.00 4. Earned Subject to Retention 9,330,279.09 767,256.71 5. Mobilization 1,200,000.00 0.00 6. Total Work Completed 10,251,129.09 7. Deductions 8. a.Contract Retentions -466,513.95 -38,362.83 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,063,765.14 728,893.88 10. Reduction Amt to Escrow 11. Payment to Escrow 466,510.00 12. Net Pymt. this Estimate 728,893.88