Dept. of Trans. PROGRESS Serial No. Contract No. 07-325-06-45 04-0120L4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 7% 14% 04-ALA-80-1.0/1.7 Federal Project: NONE Progress payment No. 04 Payment period ending: 11-20-07 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,490,173.00 3,567,720.00 2.a. Extra Work 607,350.00 400,200.00 b. Adjustment Comp. 4,265,106.96 -12,754.04 3. Materials on Hand 6,482,966.82 4,906,384.83 4. Earned Subject to Retention 19,845,596.78 8,861,550.79 5. Mobilization 6. Total Work Completed 13,362,629.96 7. Deductions -1,452,726.66 -639,901.36 8. a.Contract Retentions -1,984,559.68 -886,155.08 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,408,310.44 7,335,494.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,335,494.35