Dept. of Trans. PROGRESS Serial No. Contract No. 08-058-16-23 04-0120L4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 25% 04-ALA-80-1.0/1.7 Federal Project: NONE Progress payment No. 08 Payment period ending: 02-20-08 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,096,258.00 7,366,263.00 2.a. Extra Work 900,771.50 90,630.99 b. Adjustment Comp. 9,398,540.16 0.00 3. Materials on Hand 12,210,272.62 481,014.03 4. Earned Subject to Retention 47,605,842.28 7,937,908.02 5. Mobilization 6. Total Work Completed 35,395,569.66 7. Deductions -1,718,331.87 -304,058.95 8. a.Contract Retentions -3,250,073.22 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 42,637,437.19 7,633,849.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,633,849.07