Dept. of Trans. PROGRESS Serial No. Contract No. 09-141-07-45 04-0120L4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 75% 04-ALA-80-1.0/1.7 Federal Project: NONE Progress payment No. 23 Payment period ending: 05-20-09 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 02328 Total Estimate This Estimate 1. Contract Itms Without Mobil. 129,603,399.80 3,581,161.00 2.a. Extra Work 4,633,205.49 695,533.22 b. Adjustment Comp. 21,178,445.75 70,000.00 3. Materials on Hand 2,757,958.45 -7,990.35 4. Earned Subject to Retention 158,173,009.49 4,338,703.87 5. Mobilization 6. Total Work Completed 155,415,051.04 7. Deductions -1,879,507.01 -40,553.80 8. a.Contract Retentions -7,908,650.47 -216,935.19 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 148,384,852.01 4,081,214.88 10. Reduction Amt to Escrow 11. Payment to Escrow 7,500,000.00 12. Net Pymt. this Estimate 4,081,214.88