Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-272-07-00 04-0120L4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-ALA-80-1.0/1.7 Federal Project: NONE Progress payment No. 38 Payment period ending: 06-08-10 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 02328 Total Estimate This Estimate 1. Contract Itms Without Mobil. 158,879,300.23 1,000.00 2.a. Extra Work 12,707,522.68 438,464.63 b. Adjustment Comp. 23,862,598.55 -26,785.50 3. Materials on Hand 4. Earned Subject to Retention 195,449,421.46 412,679.13 5. Mobilization 6. Total Work Completed 195,449,421.46 7. Deductions -2,342,413.52 -126,807.37 8. a.Contract Retentions -9,677,356.72 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9,677,356.72 0.00 9. Total pay to Contractor 193,107,007.94 285,871.76 10. Reduction Amt to Escrow -9,000,000.00 0.00 11. Payment to Escrow 9,000,000.00 12. Net Pymt. this Estimate 285,871.76