Dept. of Trans. PROGRESS Serial No. Contract No. 13-110-15-24 04-0120M4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 38% 04-ALA-80-1.0/1.7 Federal Project: NONE Progress payment No. 11 Payment period ending: 04-20-13 FLATIRON WEST INC 2100 GOODYEAR ROAD BENECIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,796,968.50 1,172,525.00 2.a. Extra Work 1,902,603.14 464,520.37 b. Adjustment Comp. 3. Materials on Hand 482,690.51 181,680.65 4. Earned Subject to Retention 15,182,262.15 1,818,726.02 5. Mobilization 2,900,000.00 145,000.00 6. Total Work Completed 17,599,571.64 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,082,262.15 1,963,726.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,963,726.02