Dept. of Trans. PROGRESS Serial No. Contract No. 14-262-11-00 04-0120M4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 100% 04-ALA-80-1.0/1.7 Federal Project: NONE Progress payment No. 34 Payment period ending: 09-20-14 FLATIRON WEST INC 2100 GOODYEAR ROAD BENECIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,039,038.21 341,517.00 2.a. Extra Work 19,425,170.56 271,984.64 b. Adjustment Comp. 14,961,297.57 -137,911.47 3. Materials on Hand 4. Earned Subject to Retention 62,425,506.34 475,590.17 5. Mobilization 2,900,000.00 0.00 6. Total Work Completed 65,325,506.34 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 65,325,506.34 475,590.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 475,590.17