Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-289-08-58 04-0120M4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-ALA-80-1.0/1.7 NONE Progress payment No. 048 Payment period ending: 09-26-15 FLATIRON WEST INC 2100 GOODYEAR ROAD BENECIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,588,755.16 -3,500.00 2. a. Extra Work 23,832,464.87 46,942.51 b. Adustment Comp. 15,818,431.34 0.00 3. Materials on Hand 4. Earned Subject to Retention 68,239,651.37 43,442.51 5. Mobilization 2,900,000.00 0.00 6. Total Work Completed 71,139,651.37 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 71,139,651.37 43,442.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 43,442.51