Dept. of Trans. PROGRESS Serial No. Contract No. 04-168-11-04 04-0120Q4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 88% 04-SF-80-8.0/8.0 Federal Project: ACBR-080-1(98) IM-080-1(98) Progress payment No. 11 Payment period ending: 06-20-04 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,420,826.73 -13,049.11 2.a. Extra Work 423,882.60 44,072.04 b. Adjustment Comp. 211,136.24 0.00 3. Materials on Hand 0.00 -20,957.00 4. Earned Subject to Retention 2,055,845.57 10,065.93 5. Mobilization 141,200.00 0.00 6. Total Work Completed 2,197,045.57 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -102,792.28 -503.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,084,253.29 9,562.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,562.63