Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 07-219-13-36 04-0120R4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 74% 04-SF-80-7.8/8.2 Federal Project: ACBR-080-1(97) IM-080-1(97) Progress payment No. 42 Payment period ending: 07-31-07 C C MYERS INC P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 02172 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,578,203.53 0.00 2.a. Extra Work 32,940,143.37 14,059,504.70 b. Adjustment Comp. 19,016,845.58 0.00 3. Materials on Hand 6,572,917.43 0.00 4. Earned Subject to Retention 77,108,109.91 14,059,504.70 5. Mobilization 7,000,000.00 0.00 6. Total Work Completed 77,535,192.48 7. Deductions -20,000.00 0.00 8. a.Contract Retentions -3,855,405.50 -702,975.24 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 80,232,704.41 13,356,529.46 10. Reduction Amt to Escrow 11. Payment to Escrow 3,855,400.00 12. Net Pymt. this Estimate 13,356,529.46