Dept. of Trans. PROGRESS Serial No. Contract No. 10-207-08-49 04-0120R4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 90% 04-SF-80-7.8/8.2 Federal Project: ACBR-080-1(97) IM-080-1(97) Progress payment No. 81 Payment period ending: 07-20-10 C C MYERS INC P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 38,333,967.31 -833,515.00 2.a. Extra Work 330,458,367.16 2,565,615.58 b. Adjustment Comp. 82,526,306.14 613,425.20 3. Materials on Hand 216,177.42 -207,690.00 4. Earned Subject to Retention 451,534,818.03 2,137,835.78 5. Mobilization 7,000,000.00 0.00 6. Total Work Completed 458,318,640.61 7. Deductions -299,988.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 458,234,830.03 2,137,835.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,137,835.78