Dept. of Trans. PROGRESS Serial No. Contract No. 10-356-12-56 04-0120S4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 21% 04-SF-80-7.9/8.2 Federal Project: NONE Progress payment No. 10 Payment period ending: 12-20-10 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 956600620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,848,872.10 1,340,772.90 2.a. Extra Work 1,162,759.93 766,379.44 b. Adjustment Comp. 19,163.87 19,163.87 3. Materials on Hand 66,100.00 -1,000,000.00 4. Earned Subject to Retention 10,096,895.90 1,126,316.21 5. Mobilization 6,015,459.75 0.00 6. Total Work Completed 16,046,255.65 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,112,355.65 1,126,316.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,126,316.21